Which statement is true regarding a liquidated damages clause?
A) A provision for liquidated damages is illegal.
B) A provision for liquidated damages is void because of public policy.
C) A provision for liquidated damages is voidable because of public policy.
D) A provision for liquidated damages is enforceable so long as it is not punitive in nature.
E) A provision for liquidated damages will be enforced regardless of whether it is punitive in nature.
Liquidated Damages Clause
A contractual provision specifying a predetermined amount of damages to be paid if one party breaches the contract.
Punitive
Relating to punishment, often referring to punitive damages in legal contexts, which are awarded in addition to actual damages to punish the defendant and deter future misconduct.
Public Policy
Principles and standards considered by the government to be beneficial for the community and used as a guideline for legislative or regulatory actions.
- Understand the provision and enforcement of liquidated damages clauses and their limitations to prevent punitive measures.
Verified Answer
Learning Objectives
- Understand the provision and enforcement of liquidated damages clauses and their limitations to prevent punitive measures.
Related questions
Which One of the Following Statements Accurately Describes the Effect ...
Catherine Agreed to Purchase Franchise Rights from a Hamburger Restaurant ...
Zenia Contracts with Yvonne for a Supply of Specialized Computer ...
Renew Turf Inc ...
The Uniform Commercial Code Provides That Remedies May Not Be ...